Update here... about 12 days in. Random pics below of things along the way, but as of now...


  • Ribs and stiffeners all set in the horizontal stabilizer and elevator.
  • One wing test fit properly, geometry set at factory all good.
  • Spar stiffeners riveted on.
  • Working on lift strut brackets now.


Next up is finishing the hysol lift strut brackets. Then finish wing attachment process. Install number one rib, fuel tank, etc.

After that, flip fuse around and do the other side.

More pictures in the link in my profile.

img_0704.jpg

img_0714.jpg