Thread: Paper work needed for upgrading an engine

  1. #1

    Join Date
    Nov 2014
    Location
    Gainesville, tx
    Posts
    79

    Default Paper work needed for upgrading an engine

    I asked a question about an engine upgraded to higher horsepower (assumed it was an engine swap). Evidently the engine in question on a plane for sale is the original 582 the plane had however the cylinders and related hardware were replaced with 670 parts by Rotax Rick to make the 670 power plant. Essentially it is a big bore 582 with the original serial number for the plane. My question is what have those that have the "zipper kits" on the 9 series, or bored out engines done as far as paper work? The guy selling the plane is telling me his A&P looked over the paperwork and said most don't even upgrade the paperwork since it is the same engine same serial number, but if you did it would just be a 5 hr phase 1 fly off and file the paperwork. Opinions?
    Mark

  2. #2
    Senior Member
    Join Date
    Apr 2009
    Location
    Chisholm Mn
    Posts
    1,575

    Default Re: Paper work needed for upgrading an engine

    An engine change is considered a major change. That requires the phase 1 flight test and notifying the FAA. Being that this is the same serial #, it sounds like the same engine to me with some different parts. I don't think you need to do the major change thing. YMMV. JImChuk

  3. #3
    Senior Member
    Join Date
    Oct 2013
    Location
    Brownsburg, IN
    Posts
    544

    Default Re: Paper work needed for upgrading an engine

    What if it's the original engine, just rebuilt. Is there a 5 hours fly off and more paperwork to do?

  4. #4
    Super Moderator Av8r3400's Avatar
    Join Date
    Jan 2009
    Location
    Merrill, WI
    Posts
    3,046

    Default Re: Paper work needed for upgrading an engine

    I would doubt an engine rebuild would fall under a major change requiring a return to phase I condition.

    Check your operating limitations, anyway.
    Av8r3400
    Kitfox Model IV
    The Mangy Fox
    912UL 105hp Zipper
    YouTube Videos

  5. #5
    N981MS's Avatar
    Join Date
    Dec 2012
    Location
    Dexter, GA
    Posts
    161

    Default Re: Paper work needed for upgrading an engine

    An engine rebuild does not constitute a major change. I suspect the OPs engine modifications constitute a major change by the intent of the rule. A significant change in power will affect how the craft flies. I also suspect it may meet the letter of the law given the same serial number. I would call the FSDO with a plan to go back into phase 1 for a couple of hours.

    I have dealt with major changes and it was no big deal in our FSDO(Atlanta). We changed a prop and removed slats on a Zenith 750. Called the FSDO with our plan for 5 hours back into phase 1 with the same geographic area as original. They said OK. 5 hours of testing; climb, descent, stall, etc and log book entry and we were back in business.
    Last edited by N981MS; 09-04-2016 at 02:06 PM.
    Maxwell Duke

    Kitfox S6 IO-240 Built it (Flying since 2003)
    Maule M7-235C Sold it (liked it though)
    RV-10 IO-540 Bought it
    Zenith CH-750 Built with 7 friends (DAR Vic Syracuse)

  6. #6
    Senior Member
    Join Date
    Oct 2013
    Location
    Brownsburg, IN
    Posts
    544

    Default Re: Paper work needed for upgrading an engine

    I'm going to have to change the prop as well. The old wood prop had a TBO of five years and had been setting for ten. So I'm thinking of an IVO prop.
    Sounds like I still will have the five hours?

  7. #7
    N981MS's Avatar
    Join Date
    Dec 2012
    Location
    Dexter, GA
    Posts
    161

    Default Re: Paper work needed for upgrading an engine

    I am pretty sure a prop change is a "major change" requiring some phase I time. I do not think there is a standard amount of time. Just have a reasonable plan before you call the FSDO. I think reasonable is; enough time to test stalls at different loading. Rate of climb. Rate of descent. Of course with a ground adjustable prop you will want to test several different pitch settings. I had what I felt was a reasonable plan in mind when I called the FSDO. The guy there made some notes I guess and got our N number and that was it. A new weight and balance may be in order as well.
    Maxwell Duke

    Kitfox S6 IO-240 Built it (Flying since 2003)
    Maule M7-235C Sold it (liked it though)
    RV-10 IO-540 Bought it
    Zenith CH-750 Built with 7 friends (DAR Vic Syracuse)

  8. #8
    FoxDB's Avatar
    Join Date
    Aug 2010
    Location
    Malad, ID
    Posts
    85

    Default Re: Paper work needed for upgrading an engine

    The 670 cylinders will not fit on a 582 Block. A 670 crank will not fit a 582 block either. So it is a different engine.